What is one activity the Release Train Engineer (RTE) performs before an upcoming PI?

  1. Facilitate ART Backlog prioritization with Product Management and other stakeholders

  2. Provides approval and sign-off for draft Team Backlogs

  3. Ensures at least 30% of the ART Backlog is allocated to Enabler Features

  4. Allocates time in the Coach Sync for Product Management to socialize with the teams on the Features

The correct answer is: Facilitate ART Backlog prioritization with Product Management and other stakeholders

The Release Train Engineer (RTE) plays a crucial role in preparing for an upcoming Program Increment (PI), and one of the key activities involves facilitating the prioritization of the Agile Release Train (ART) Backlog. This activity requires collaboration among Product Management and various stakeholders to ensure that the features and user stories in the backlog are appropriately prioritized based on business value, needs, and resources. Through this facilitation, the RTE helps to align everyone on the vision and objectives of the upcoming PI, ensuring that the ART has a clear direction and focus. This prioritization process is essential for maximizing the value delivered during the PI, as it establishes what the teams will work on first based on stakeholder input and strategic goals. By promoting open communication and collaboration among all parties involved, the RTE reinforces the collective ownership of the backlog, leading to more effective planning and execution during the PI. Prioritizing the ART Backlog with input from Product Management and stakeholders also enhances transparency and fosters a shared understanding of priorities, which is critical for ensuring that the teams are aligned with the overall goals of the organization. This preparatory work helps set the stage for a successful PI planning event, contributing to a smoother execution of the increment.