What information is covered during the final plan review?

  1. Changes to capacity and load, final PI Objectives, ART PI Risks, and impediments

  2. Team Features, Stories, and team-level Enablers

  3. Planned Features, uncommitted objectives, and ROAMed risks

  4. Changes to Iteration Goals and measured velocity

The correct answer is: Changes to capacity and load, final PI Objectives, ART PI Risks, and impediments

The final plan review focuses on critical elements that help the Agile Release Train (ART) assess its preparedness for the upcoming Program Increment (PI). This includes discussing changes to capacity and load, which reflects the team's ability to take on new work based on their past performance and any adjustments made. Reviewing the final PI Objectives is essential, as these objectives guide the train's focus and priorities for the upcoming increment. Additionally, identifying ART PI Risks and impediments in the final review allows teams to proactively address potential challenges that could hinder their progress. Together, these components facilitate alignment among teams, ensuring that everyone is aware of current capacities, objectives, and risks, thereby maximizing the chances of success in the upcoming PI. The final plan review acts as a comprehensive wrap-up that enables the ART to enter the next increment with confidence and clarity. This thorough overview is a fundamental part of the SAFe methodology, aligning all stakeholders on the intent and readiness for the work ahead.