What hourly activity helps keep teams on track during the Team Breakout portion of PI Planning?

  1. Coach Sync

  2. Business Owner feedback meeting

  3. ART planning board inspection

  4. Iteration Review

The correct answer is: Coach Sync

The activity that helps keep teams on track during the Team Breakout portion of PI Planning is the Coach Sync. This engagement serves as a crucial mechanism for facilitating communication and coordination among the various teams within the Agile Release Train (ART). During the Coach Sync, Release Train Engineers (RTEs), Scrum Masters, and other coaches come together to share insights, address any challenges, and ensure alignment across teams. This hourly check-in provides a structured opportunity for teams to voice concerns, ask questions, and adjust their plans based on feedback and observations from other teams or leadership. It fosters a sense of cohesion and collaboration, which is essential for maintaining momentum and helping teams navigate the complexities of PI Planning. Moreover, the regularity of the Coach Sync allows for real-time feedback and the ability to pivot or refine plans as needed, rather than waiting until the end of the breakout sessions. It ultimately aids in minimizing potential roadblocks that could hinder the completion of objectives during the Program Increment. Other activities, while valuable in their own contexts, do not specifically provide the same level of ongoing guidance and alignment during the active planning process on an hourly basis.